Shale Shaker Screens replacement method

Author:hengyingwirecloth 2021-09-15 10:40:12 179 0 0

Method of changing fine mesh

1. First loosen the screw of the bundle ring, remove the upper frame, remove the damaged fine mesh, and replace it with a new fine mesh.

2, the fine mesh tiled in the Shale Shaker Screens mother network, put the upper frame back to the original position, in the vicinity of the fine mesh by hand, at both ends of the fuselage of the upper frame and the lower frame of the frame edge, each with a universal pliers, the upper frame and the lower frame clamp.

3, the Shale Shaker Screens around the edge of the prominent frame of the fine mesh in addition to reserved two centimeters, the rest of the cut off.

4. Re-set the bundle ring, loosen the universal pliers, hook the bundle ring screw and lock it tightly.

5, with a soft hammer evenly beat around the beam ring, and then the copper nut lock, the fine mesh is completed. If in the process of changing the Shale Shaker Screens, there is the mother grid and moving plate is removed, it must be paid attention to the moving hole plate must be indeed embedded in the flange of the bottom of the grid.

84f3350f37b85fbcf0670c50b7d19055.jpg

Change the method of the mother network

If the Shale Shaker Screens is damaged, it can be repaired by itself. If it can not be repaired, please return to the factory for repair. It is advisable to prepare a group of bus network for backup.

Installation of screen mesh on frame

The frame of the screen installation is "field" glyph, the upper and lower two are consistent, the screen is clamped in the middle, and the bolt is fixed around the frame. At the same time, up and down the frame and screen all padded old book conveyor belt, improve the phenomenon of vibration broken thick wire.